EP3
EP-3 Phase 1
- Basic Engineering completed in Q-4-2011 to increase the capacity of Ethylene Plant from 720 KT/y to 900 KT/y.
- Replacement of existing 7 furnaces EPC contract in place and ready for feed will be June 2014.
- New Ethylene Tank for 50,000 M3 EPC contract in place and will be ready in Q-3 2014.